One of our projects

Musturd ERC(Egyptian Refinery Company) Main Contractor to middle East co - Orascom Construction:

  • MECS responsible for all piping installation activity in utility area, supervision, skilled man power, equipment, to achieve the required targets.
  • We Hand over our area according to our contract schedule to be the first area start commissioning in the whole projects.
  • Main contractor: GS & Orascom.
  • Contract Schedule: 1 year.
  • Progress achieved: 85% in 7 months.
         MECS Scope completed in contract date.